To:
Owens, Will (Duckworth) <Will_Owens@duckworth.senate.gov>
Cc: Posovich, Michael S CIV USARMY CENWP (US) <Michael.S.Posovich@usace.army.mil>
Subject: RE: Status of Gate Blade Optimizer Project (UNCLASSIFIED)
CLASSIFICATION:
UNCLASSIFIED
Good
Morning Mr. Owens,
GBO
development has been on-going. The presentation from 2011 indicated a 3-4 year
timeline to develop cam tables for 97 units. This was overly optimistic.
Evolving GDACS security protocols as well replacement of 3D Cam controllers
with digital governors have necessitated re-designs to the GBO. This includes
different platforms, hardware changes, and reprogramming. Latest generation
proof-of-concept GBO has been largely complete for several years. Currently,
the latest generation GBO is installed on one unit at The Dalles
Powerhouse. Due to numerous reasons (e.g. limited range of operation during
fish passage season, limited head range seen at the project, unexpected unit
outages) data collection over several years has been required to obtain
sufficient information to develop updated cam information. In order to
validate proof of concept results index testing is recommended but has not been
performed. Until validated GBO will not be installed on additional units.
Please
let me know if you need anything else.
Regards,
Andrew
Long, P.E., C.E.M.
Product
Coordinator
U.S. Army
Corps of Engineers
Hydroelectric
Design Center
333 SW
1st Ave, Portland, OR 97204