There is a test procedure for hydroelectric turbines
called "index testing" that is documented in the American
Society of Mechanical Engineers (ASME) Performance Test Code (PTC), PTC-18.
This is accompanied by turbine control system testing procedures in ASME
PTC-29. Performance limits for the turbine control systems are delineated
by the Institute of Electrical and Electronics Engineers (IEEE) Std-125
& Std-1207 standards.
These procedures and standards will determine the
optimum-efficiency head and wicket gate to blade relationship for a Kaplan
turbine under varying head and power conditions, and assure that the control
system is robust and precise in controlling the turbines by providing
measurement procedures and quantified standards (or limits) for comparison.
These tests and standards were developed to maximize
electrical output and minimize the environmental impact of Kaplan
turbines.
These are both American National Standards, approved
by the American National Standards Institute (ANSI) for this type of equipment.
In my opinion, these procedures and standards should certainly be adhered to by
the U.S. Army Corps of Engineers (USACE) in their management of the turbines
along the Snake and Columbia Rivers, but they are not.
Best practice - every single Kaplan turbine should be index-tested
and optimized (or tuned-up) upon original installation, and then
periodically every five years thereafter to ensure continued
peak performance in these two areas. However, this is not the case in the
Corp of Engineers' powerplants. Most of these turbines have never been index
tested. In practice, USACE only index tests 1 or 2 turbines of each family
in every powerhouse about every 7 years. Typically, operating efficiency losses
of from 2% to 3% are found, resulting from misalignment of the gates and blades
away from their optimum relationship.
To worsen this situation, even after the Corps index tests the
turbines and identifies the 3-D cam (The term “3-D cam” refers to the feature
in the turbine governor that controls the blade to head and wicket gate
relationship) surface misalignment, they do not update the 3-D cam surfaces to
achieve the highest possible operating efficiency for the turbines; they just
leave them as-found.
Another issue is that USACE is predominantly using
one supplier, Automated Control Systems Incorporated (ACSI) of Vancouver,
Washington, for their control system work. There is no clear justification for
the apparent favoritism towards this one contractor, which has developed
and deployed the 113 Kaplan turbine blade control systems currently in use
at all Corps Snake and Columbia River powerplants. The observations I made
while working with the Corps on their turbines in the two worst fish-mortality
powerplants, McNary and Ice Harbor indicate that the turbine control
system equipment is sub-standard and the Corps is covering it up.
I know this from firsthand experience; I was there, and measured
the performance of two of their turbines and control systems with my
patented automatic Index Test Box (ITB) for Kaplan Turbines (Patent#
4,794,544 was awarded in 1987 while I was working for the Woodward
Governor Company). After the patent expired, USACE contracted (USACE
contract # W9127N-04-D-0009) with my Actuation Test Equipment Company in 2004 to buy an
updated ITB from me. This new instrument was demonstrated successfully on unit
9 at McNary Dam in December 2005 and again on unit 3 at Ice Harbor
Dam in February 2006.
During these tests we saw that the blade control systems that
USACE’s Hydroelectric Design Center (HDC) and ACSI developed and deployed
are substandard; they do not meet the ANSI/IEEE performance standards as
measured by the ANSI/ASME test procedures for turbine control
systems. This substandard performance manifests in unstable turbine
operation - the turbine's gates and blades hunt and oscillate uncontrollably,
which causes premature wear on the turbine blade trunion bearings. Replacing
these bearings requires dismantling the generator and pulling the turbine out
of the hole in the floor – which is a long, expensive and difficult procedure.
This is especially unwelcome when the wear causes a breakdown,
necessitating unscheduled maintenance on the unit.
To prevent this hunting, oscillation and subsequent wear, HDC
and ACSI have added “deadband” and "deadtime" functions to the blade
control algorithm. At McNary Dam, the deadband is set to 1.0 degree, out of a
15.5-degree arc of full blade rotation. By the ASME method of deadband
measurement, which sums the error on both sides, the 1.0 degree deadband is
actually 2% deadban ; there is also a 35
second delay (deadtime) before the 3-D cam responds to changes in head or gate.
The IEEE industry standard (as measured using the ASME procedures and met
by all other turbine control system suppliers) is 1.0% of the span of blade
rotation, or approximately 1/15th of the deadband seen in the Corps' units at
McNary Dam. The standard for deadtime is 0.2 seconds, or 1/175th the
deadtime seen at McNary Dam.
This was and is a bad solution; when people in the hydro
industry learn about these improper engineering practices, there is much
laughter and derision. Then a few wisecracks about "close enough for
Government work," but it's not funny.
This control system deficiency, combined with the misalignment of
the 3-D cam surface resulting from USACE's failure to index test and
optimize each of them periodically, on an individual basis, results in
lost efficiency and greatly increased turbulence in the water flowing
through the turbines.
This increased turbulence makes turbine passage much more
hazardous for the downstream migratory fish, which seems to be
the crux of the Federal lawsuit. To describe it succinctly - during times
of the year when extremely endangered species are migrating downstream, the
Corps isn't allowed to run the turbines at all. Per the BiOp and your
corresponding court order they must open the spill gates to minimize the hazard
to these fish.
Marine biologists have agreed that minimizing the turbulence by
operating at the turbine's highest efficiency point reduces the turbulence and
hazard to the fish, which is a fundamental concept written into the BiOp. Thus,
during periods of the year when marginally endangered species are
migrating downstream, the BiOp allows operation only within the top
1% of the efficiency envelope.
The substandard performance of the control systems and the
misalignment of the blades, both of which factors (I witnessed and have
documented) prevent the Corps from operating the turbines within the top 1% of
the efficiency envelope. Because they don't index test every turbine
individually, they are not even certain where the operating efficiency
peak is on each of them. The Corps just made their best guess, took their
best shot, then told you they were in compliance with the BiOp terms.
This is a falsehood - by my data and
analysis they're not even close.
On unit 9 at McNary Dam, misalignment of
the 3-D cam surface for the gates and blades and the substandard control
equipment has reduced operating efficiency by approximately 2%. They simply
cannot get to within 1% of the efficiency peak of the machine. By the BiOp and
your court order, they should not be operating these units at all.
The problems I'm trying to bring to light are
exacerbating factors to the fish mortality problem. The industry standards
are intended to prevent this sort of thing from happening, but they were
circumvented by USACE designing their own control systems for these turbines
and using a “captive supplier” (ACSI) to deploy this equipment, instead of
purchasing it through a proper open solicitation and bidding process from
reputable suppliers and specifying the applicable industry standards.
When USACE bought similar equipment from Woodward Governor Company
on a legitimate Purchase Order (P.O.) in 1980, the contracting officers
wrote the industry standards into the P.O. to assure they would get equipment
that operated properly by specifying the industry standard 1.0% deadband and
0.2-second deadtime.
The machinery at McNary, purchased on a blanket P.O. from ACSI,
has an excessive 15% deadband and 35 second deadtime.
When I brought this substandard equipment to USACE IG's attention,
they excused this by telling me that because the “blanket” purchase order
didn't have the industry standards written into it, there was no violation of
the provisions of the acquisition documents, so there was nothing the IG could
do about it. I argued the point about industry standards and non-compliance
with your court order, but to no avail.
Perhaps my complaints should have been against the
contracting officer for allowing such sloppy equipment to be purchased and
deployed without utilizing the proper safeguards provided by the industry
standards. To my mind this is a root-cause of the fish mortality
problem.
I am currently reporting this situation to DOD IG, which is senior
to Army IG, which is in turn senior to USACE IG. This multi-level bureaucracy
has been very effective in thwarting any criticism that they do not want to
deal with, but some small progress is being made.
Though not a panacea, it is a certainty that this dire situation
can be improved significantly by addressing the mortality problem at the point
where the killing actually occurs - at the passage through the turbines.
Sincerely yours,
______________________________
Douglas J. Albright – President
Actuation Test Equipment Company